NEW CHURCH BUILDING DEVELOPMENTS
People of GOD are building the state-of-the-art one storey house of the LORD for worshipping and we are at a stage building first floor, you are kindly invited to share this blessings by contributing anything materials or cash and will give you a feedback on what was the impact of your contribution. MAY GOD BLESS YOU!
Sunday, October 30, 2011
Sunday, September 18, 2011
Friday, August 26, 2011
THE GREAT GOSPEL MEETING AT SHAMSI BAPTIZED 71 PEOPLE
The Great gospel meeting ran by SHAMSI SDA church members for three weeks between 07/16/2011 06/08/2011 successfully accomplished by baptizing about 71 spirits who made a firm decision to surrender and buried their old dignity and chosen the new one in JESUS name, let the name of the Lord be blessed.
MCHUNGAJI LAIZER AKIMBATIZA MMOJA WA WALIKATA SHAURI NA KUAMUA KUUZIKA UTU WAO WA KALE NA KUCHAGUA UTU UPYA.
Mkutano Mkubwa wa injili ulioendeshwa na washiriki wa kanisa la SHAMSI kwa takriban wiki tatu (3) kati ya 16/7/2011 na 6/8/2011 wamalizika kwa kuongoa roho 71 zilizokata shauri na kubatizwa, Jina la BWANA litukuzwe.PART OF THE GOSPEL multitude ran by PASTOR KINANA FOR THREE WEEKS at Shamsi grounds
SEHEMU YA UMATI MKUBWA WA INJILI ULIOENDESHWA NA MCHUNGAJI KINANA KWA WIKI TATU
picha zaidi
Tuesday, June 21, 2011
CONSTRUCTION OF BEAMS WORKS BEGAN
KAZI YA UJENZI WA NGUZO YAANZA
Wiki inayooshia tarehe 26/06/2011 matoleo ya watu wa Mungu yamewezesha kumwaga zege katika beams kama inavyoonekana hapa chini:
Kabla ya zege kumiminwa katika bimu kazi ya kusuka nondo ilikamilika wiki iliyooshia tarehe 18/06/2011 kama inavoonekana katika picha hapa chini:
Watu wa Mungu....Mbarikiwe saana mnapoendelea kujitoa kwa hali na mali kumjengea BWANA hekalu takatifu...wiki inayoishia tarehe 18/06/2011 Mungu amewezesha kupitia matoleo yako kazi uionayo hapo juu...Mungu akubariki anapopanga kuendelea kutoa kwa ajili ya kuwezesha usukwaji zaidi wa nondo hizo juma hili....kwa picha na habari zaidi bofya hapa chini....
Tuesday, June 7, 2011
Kwa sasa kazi ya awamu iliyoko mbele yetu inayoanzia tarehe 12/06/2011 itagharimu takribani TShs. 48,150,000 , kazi iliyokwisha kukamillika ikijumuisha sehemu ya nguvu kazi ya kujitolea ina thamani ya Shs. 55,500,000. Jumla ya gharama zote za mradi mpaka kukamilika ni Shs. 266,378,000. Mchanganuo wa kazi ya awamu hii kwa sasa ya Shs. 48,150,000 ni kama ifuatavyo:
s/n Material Gharama (TShs) 1. Nondo R16 20, 000kgs @ Tshs 1, 600/= per kg 32,000,000 2. 230 bags of cement @ tshs 16, 000 3,220,000
3. 150 kgs Binding wires @ Tshs 3, 000 450,000 4. 1\2” Kokoto 140 tons @ Tshs 42, 857/=(lorries 20) 6,000,000 5. 280 tons Mchanga…(lorries 40 @ Tshs 70, 000/=) 2,800,000 6. 300 Mirunda @ Tshs 5, 000 1,500,000 7. 60 Kgs Misumari (3”-1 ½”) @ Tshs 3, 000 180,000 8. 400 Mbao rejects) for formwork (various sizes) 2,000,000 TOTAL 48,150,000
Mchanganuo wa mahitaji yoote ya mradi mzima kwa maana ya BOQ bofya kwenye habari zaidi...
Tuesday, May 31, 2011
Sunday, May 29, 2011
Sunday, January 23, 2011
Subscribe to:
Posts (Atom)
Labels
NEWS
EVENTS ON PICTURES/ MATUKIO PICHA
EFFORT ILIYOBATIZA WATU 71
DRAWINGS FOR THE NEW CHURCH/ KANISA TARAJIWA
USEFUL LINKS
CHURCH HISTORY
ADVERT
CHAGUA YESU MAISHANI MWAKO
|